Project Title | POWER PLANT FOR COGENERATION OF THERMAL AND ELECTRICAL ENERGY 15,5 MW IN REVITHOUSA |
Project Area | GREECE - ATHENS –Revithousa Island |
Project Cost | 16.500.000 € |
Project Owner | Manager of Natural Gas National System (DESFA S.A.) |
Project Main Contractors | BURMEISTER & WAIN SCANDINAVIAN CONTRACTOR A/S (BWSC) |
Client | ELEMKA S.A. |
Time Schedule | 12 Months (achieved ahead schedule) Mid 2008 – mid 2009 |